Team agreements · FREE FIELD KIT

RACI template with a filled example, Excel checks and a 45-minute session

A RACI template is a grid that lists the tasks of one project down the side and the people or roles across the top, and marks who does each task (R), who answers for it (A), who is asked first (C) and who is told (I). This kit gives you a blank RACI grid, a filled example from a fictional course launch, checks for exactly one A and at least one R per task, a load check per person and a 45-minute session to agree the grid.

Updated · Template

45 minutes3–10 participantsOnline + adaptable in person
OPEN ACCESS · NO FORMRACI template (PDF)

Filled example: agreed RACI grid

A fictional learning team launches a course on handling customer complaints. Every row has exactly one A and at least one R. Empty cells mean the role is not involved.

#Task or decisionSponsorLearning leadCourse designerLead trainerCoordinatorSite managersIT supportCheck
T1Agree the course objectives and how success is judgedARCCICOK
T2Write the session plan and participant materialsARCOK
T3Approve the final materialsACRCOK
T4Run the pilot session and collect feedbackARRIOK
T5Agree the dates of 12 sessions across three sitesICCA/RCOK
T6Book rooms and equipment at each siteIA/RCOK
T7Release staff from the phones to attendICIA/ROK
T8Send invitations and joining instructionsIIA/RIOK
T9Set up the online pre-course quizIA/RCOK
T10Deliver the sessionsARCIOK
T11Track attendance and follow up people who missed a sessionIA/RCOK
T12Report results to the sponsor after the first monthIA/RCCOK

RACI grid

Blank version. Copy it into a document or a spreadsheet, or use the Excel grid, which runs the checks for you.

#Task or decisionRole 1Role 2Role 3Role 4Role 5Role 6Role 7Role 8Check
T1One A? An R?
T2One A? An R?
T3One A? An R?

What each letter means

RACI is a widely used convention for sharing out responsibility; it has no single owner or author. The wording, the questions and the checks here are written for this kit.

LetterWhat it means hereThe question that settles itCommon mistake
R: ResponsibleDoes the work, or makes sure it gets done.“Who will actually do this next week?”Several Rs and nobody leading them, or an R for a group with no contact.
A: AccountableThe one person who answers for the result, signs it off and can say no.“If this goes wrong, who will be asked why?”Two As, or an A given to a committee, so nobody decides.
C: ConsultedAsked for a view before the work is final. Two-way.“Whose view could change the result?”Everyone is consulted, so the work waits for many replies.
I: InformedTold when the work is done or decided. One-way.“Who needs to know, but not to agree?”People marked I expect to be asked, because nobody explained the difference.
A/RThe same person answers for the result and does the work.“Is this small enough for one person to own and do?”Used on large tasks, so nobody checks the work.

Checks to run on a RACI chart

The Excel workbook runs all five checks. On paper, count by hand in step 4 and step 6 of the session.

CheckRule in this kitWhat a failure usually meansWhat to ask
One A per rowExactly one A or A/R on every rowNo A: nobody can say it is done. Two As: a hidden disagreement.“If this goes wrong, who will be asked why?”
At least one R per rowOne or more R or A/R on every rowThe A expects someone else to do the work.“Who will do this, and do they know?”
Consulted limitNo more than 3 Cs on a row (you set the number)The task waits for comments from too many people.“Whose view could change the result? Can the others be informed?”
Load per personNo more than 5 rows with R or A per person (you set it)One person is a bottleneck, often without saying so.“What will you hand over or stop, or what makes this load fine?”
Empty columnEvery role column holds at least one letterThe role is not needed, or a task is missing.“Is a task for this role missing?”

Filled example: draft RACI grid with checks

The draft before the session. Four rows fail a check: T1, T3, T6 and T9.

#Task or decisionSponsorLearning leadCourse designerLead trainerCoordinatorSite managersIT supportCheck
T1Agree the course objectives and how success is judgedARCCCCMore C than the limit.
T2Write the session plan and participant materialsARCOK
T3Approve the final materialsAARCMore than one A.
T4Run the pilot session and collect feedbackARRIOK
T5Agree the dates of 12 sessions across three sitesIACRCOK
T6Book rooms and equipment at each siteIRCNo A.
T7Release staff from the phones to attendICIA/ROK
T8Send invitations and joining instructionsAIRIOK
T9Set up the online pre-course quizACCNo R.
T10Deliver the sessionsARCIOK
T11Track attendance and follow up people who missed a sessionARCOK
T12Report results to the sponsor after the first monthIA/RCCOK

Filled example: load check

Rows with R, A or A/R per role, before and after the session. The learning lead went from 10 to 5.

RoleRows with R or A: draftRows with A: draftDraft against the limit of 5Rows with R or A: agreedRows with A: agreedWhat changed and why
Sponsor22Within22No change. Keeps the A on objectives and on sign-off of the materials.
Learning lead109Above54Above the limit of 5 in the draft. Handed four tasks to the coordinator and the quiz to the course designer.
Course designer30Within41Took on the pre-course quiz (T9) as A/R. Agreed in the session.
Lead trainer20Within20No change. The open question on cover for sick days sits with the learning lead.
Coordinator40Within44Same load, but now answers for the four tasks they already did: dates, rooms, invitations, attendance.
Site managers11Within11Only one A/R, but it is the task most likely to slip: releasing staff from the phones.
IT support00Within00No R or A. Consulted on quiz access only; the column stays so IT sees the request.

Filled example: changes agreed in the session

Seven agreed changes and one open question, from the fictional session on Wednesday 14 October 2026.

#RowWhat the check or the group foundWhat we agreedConfirmed byStatus
1T1Four people marked C. Objectives would wait for four sets of comments.The coordinator moves from C to I. Three people are consulted.CoordinatorAgreed
2T3Two As: the sponsor and the learning lead both thought they signed off the materials.The sponsor keeps the A. The learning lead is consulted before sign-off.SponsorAgreed
3T5The learning lead held the A on dates the coordinator already arranges.The coordinator holds A/R. The learning lead is consulted.CoordinatorAgreed
4T6No A. Nobody could say when room booking was finished.The coordinator holds A/R. Site managers are consulted on rooms.CoordinatorAgreed
5T8The learning lead held the A on routine messages that the coordinator writes.The coordinator holds A/R. The learning lead is informed.CoordinatorAgreed
6T9No R. Everyone assumed IT would build the quiz; IT expected to be asked only.The course designer holds A/R and builds the quiz. IT is consulted on access.Course designerAgreed
7T11The learning lead held the A, but the coordinator already keeps the attendance list.The coordinator holds A/R. The learning lead is informed of no-shows each week.CoordinatorAgreed
8T10Not a letter problem: nobody knew who covers a session if the lead trainer is ill.Open. The learning lead names a cover trainer by Friday 23 October.Learning leadOpen

What you'll leave with

In 45 minutes a project team of 3–10 people has a RACI grid for one project in which every task has exactly one A and at least one R, a load count for each person with any overload discussed, and a written list of changes and open questions, each with a person who confirms it.

Before the session

  • For trainers, facilitators and project leads who help a project team of 3–10 people agree who does what on one project, soon after the kickoff.
  • Ask the project lead to draft the grid a day ahead: 10 to 12 tasks, each starting with a verb, and one column per role. Gaps are fine; the session finds them.
  • Share the draft, the letter guide and the checks in one document, or print one copy per person. Fill the workbook as you go, or tick the Check column by hand.
  • Send the draft a day early as plain text for screen readers; letters carry the meaning, not colour. Allow written comments, let people pass, keep cameras optional. The grid covers this project only.

How to fill it in with your team

01 / 4 MINUTES

Open and agree what the letters mean

Say: “We will leave with a grid for this project that says who does each task, who answers for it, who is asked first and who is told. It covers this project only. It is not a job description.” Read the letter guide aloud, one line per letter. Stress the two rules: each task has exactly one A, and at least one R.

02 / 6 MINUTES

Check the task list

Read the task list aloud. Ask: “What is missing? What is two tasks written as one?” Add missing tasks and split any task that has two owners in practice. Each task starts with a verb. Stop at about 12 rows; group small tasks rather than adding more rows.

03 / 8 MINUTES

Read your own column in silence

Give eight minutes of silence. Each person reads down their own column and marks every row where they disagree with a question mark and a short note, in pencil, in a comment or in the chat. Say: “Read your column as a promise. Would you sign every letter in it?” Nobody has to explain a mark yet.

04 / 8 MINUTES

Run the row checks

Go row by row, quickly. For each row read the Check column, or count by hand: one A, at least one R, no more than three C. Write each row that fails a check, and each row with a question mark from step 3, on the sheet “Changes and open questions”. Do not fix anything yet; this step only builds the list.

05 / 12 MINUTES

Settle the flagged rows

Take the flagged rows in task order, about two minutes each. For a missing or double A ask: “If this goes wrong, who will be asked why?” For a missing R ask: “Who will do this next week, and do they know?” For many Cs ask: “Whose view could change the result?” Write the change and the person who confirms it. If a row is not settled in two minutes, mark it Open and name who decides and by when.

06 / 5 MINUTES

Check the load per person

Count each column: how many rows hold an R, an A or an A/R. Read the counts aloud against the limit the team chose (five in the example). For anyone above it ask: “What will you hand over, or what makes this load fine?” Record the answer. A person may accept a high load; the point is that the team knows.

07 / 2 MINUTES

Read back and close

Read back the changes, the open questions with their owners and dates, where the grid is kept, and the date of the first review. Ask each person to confirm their column with a word aloud, in the chat or in writing afterwards. Passing now and confirming in writing later is fine.

Participant worksheet

Copy this table into a document, or print the worksheet from the bundle. Share only what you choose.

ItemDetail
Task list10 to 12 tasks or decisions for one project, each starting with a verb
Role columnsOne column for each role or person who holds a letter
LettersR does the work, A answers for it, C is asked before, I is told after; A/R for both
Row checksExactly one A and at least one R on every row; no more than three C
Load checkRows with R or A per person, against a limit the team sets
Changes and open questionsWhat changed, who confirms it, and what is still open

Debrief questions

  • Which row surprised us most when we read our own columns, and why had nobody raised it before?
  • Where did we have two As or none, and what would have happened if we had not found it?
  • Who is above the load limit, and what have we agreed to hand over or accept?
  • Which open question must be settled first, and who will tell the rest of us when it is?

Adapt it for your group

  • For three or four people, go down the grid together, but ask each person to read their own column before anyone speaks.
  • For a 25-minute version, ask people to mark question marks before the session, then run the checks and settle the flagged rows only.
  • Online, share the workbook on screen and collect question marks as comments or in the chat. Read each flagged row aloud. Cameras optional, captions on.
  • For quiet participants and people working in a second language, collect question marks in writing and read them out without names. Anyone can pass and confirm their column in writing after the session.
  • For more than 12 tasks, split the grid by phase or workstream and run the session once for each.

After the session

Send the agreed grid and the changes list the same day and keep the grid where the team can read it. Chase each open question by its date. Review it at the first milestone or when someone joins or leaves: read the Check column and the load row, and move letters where the work has moved. When a task slips, look at its row before asking who dropped it.

Questions people ask

What is the difference between responsible and accountable?

The responsible person does the work. The accountable person answers for the result: they sign it off, can say no and are asked why if it goes wrong. On a small task one person can be both, written A/R. Several people can be responsible; only one is accountable.

Can a task have more than one accountable person?

Not in this template. Two As usually hide a disagreement. If two people really share a decision, split the task into two rows, or give one the A and consult the other.

How is this different from the team charter template?

The team charter template records how a team works in general: purpose, decision types, communication and review. This RACI template goes task by task through one project and checks every row. Use it after the project kickoff meeting agenda, which names one owner per role.

When is a RACI chart the wrong tool?

When the work changes every week, when two or three people talk daily, or when the real question is about pay, grading or performance. It is not a job description or an HR document.

What is included in the free and editable files?

The open PDF has the blank grid, load check and changes sheet, the filled examples, the letter guide, the checks and the 45-minute session. Subscribers also receive the editable Word file, an Excel workbook that runs every check with letter drop-downs, and a CSV of the agreed example grid.

How to use the files

Print the PDF, edit the Word file in Word or Google Docs, or open the CSV or XLSX in a spreadsheet. Open files need no email.

Can I use this with paying clients?

Yes. Use and adapt this original Superglue kit in your own training, including paid client sessions. Please share this page rather than redistributing the unmodified kit. Read the full usage terms.

Created by Superglue · Original facilitation material · Updated 2026-10-10. Adapt timings and prompts to your participants; this resource has not been independently evaluated.